Owner: University of Florida
Size: 140,000 CFM
Construction Cost: $2,10,000
Twelve chilled water AHUs serving offices, conference rooms, and laboratories were replaced in two animal research buildings. Two of the units (100% OA units) were sized for future expansion in the buildings. Associated ductwork and piping was replaced in the seven mechanical rooms where the units were located. New DDC controls were provided for each unit in lieu of previous pneumatic controls. Electrical and Fire Protection systems were modified as required to accommodate the new replacements.
Lebo Engineering LLC
Copyright © 2023 Lebo Engineering LLC - All Rights Reserved.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.